Novarly ParcelRenewable sites

Renewable sitesWhitelaw Brae Wind Farm

Whitelaw Brae Wind Farm

Whitelaw Brae Wind Farm is under construction in Scottish Government (S36) with a recorded capacity of 57 MW.

57 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Wind Onshore
Technology
Thrive Renewables
Scottish Government (S36)
Authority
Scotland

Planning and build timeline

Application submitted2015-01-19
Permission granted2017-12-07
35 months after submission
Operationalnot recorded

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Clyde Wind Farm Extension (Clyde 2)
Wind Onshore · Operational
172.84.8 km
Clyde Wind Farm
Wind Onshore · Operational
3505.3 km
Glenkerie Wind Farm
Wind Onshore · Operational
228 km
Priestgill Wind Farm
Wind Onshore · Under Construction
46.210.9 km

How big is Whitelaw Brae Wind Farm?

Whitelaw Brae Wind Farm has a recorded installed capacity of 57 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Whitelaw Brae Wind Farm?

REPD records the operator as Thrive Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Whitelaw Brae Wind Farm approved and built?

The application was submitted on 2015-01-19. Permission was granted on 2017-12-07, 35 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3317.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council