Clyde Wind Farm

Clyde Wind Farm is operational in Scottish Government (S36) with a recorded capacity of 350 MW, and has been generating since 2012-10-01.

350 MW
Capacity
as recorded in REPD
Operational
Status
since 2012-10-01
Wind Onshore
Technology
Scottish and Southern Energy (SSE)/ Greencoat UK Wind
Scottish Government (S36)
Authority
Scotland

Planning and build timeline

Application submitted2004-10-01
Permission granted2008-07-21
46 months after submission
Operational2012-10-01
50 months after consent

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Whitelaw Brae Wind Farm
Wind Onshore · Under Construction
575.3 km
Clyde Wind Farm Extension (Clyde 2)
Wind Onshore · Operational
172.87 km
Priestgill Wind Farm
Wind Onshore · Under Construction
46.210.3 km
Glenkerie Wind Farm
Wind Onshore · Operational
2213.3 km
East Kilbride - Battery storage
Battery · Under Construction
49.913.6 km

How big is Clyde Wind Farm?

Clyde Wind Farm has a recorded installed capacity of 350 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Clyde Wind Farm?

REPD records the operator as Scottish and Southern Energy (SSE)/ Greencoat UK Wind. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Clyde Wind Farm approved and built?

The application was submitted on 2004-10-01. Permission was granted on 2008-07-21, 46 months later. The site became operational on 2012-10-01, 50 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4011.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council