Pitkevy Farm - Battery Storage Facility is under construction in Fife.
Planning and build timeline
| Application submitted | 2021-08-31 |
| Permission granted | 2022-01-27 5 months after submission |
| Operational | not recorded |
Fife’s record on battery storage
Fife has decided 23 battery storage schemes and approved 96%, taking a median of 3.9 months. See every battery storage scheme decision in Fife →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Balsillie Avenue - Roaring Hill Energy Storage Facility Battery · Under Construction | 19.9 | 0.8 km |
Markinch Biomass CHP Plant Biomass (dedicated) · Operational | 65 | 3.3 km |
Finmont Service Reservoir Solar Photovoltaics · Operational | 0.3 | 3.8 km |
Inchdairnie Anaerobic Digestion · Operational | 2 | 3.9 km |
Skeddoway Farm Wind Turbine Wind Onshore · Operational | 1.5 | 6.1 km |
Noble Foods Wind Onshore · Operational | 1.5 | 6.3 km |
West Strathore Solar Limited Solar Photovoltaics · Operational | 5 | 6.5 km |
Middle Balbeggie Wind Turbines Wind Onshore · Operational | 6.4 | 7.2 km |
How big is Pitkevy Farm - Battery Storage Facility?
REPD does not record an installed capacity for Pitkevy Farm - Battery Storage Facility.
Who operates Pitkevy Farm - Battery Storage Facility?
REPD records the operator as Intelligent Land Investments. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Pitkevy Farm - Battery Storage Facility approved and built?
The application was submitted on 2021-08-31. Permission was granted on 2022-01-27, 5 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7939.