Renewable sites › Bessy Bell Extension
Bessy Bell Extension
Bessy Bell Extension is an operational 9 MW onshore wind farm in Derry City and Strabane, generating since 24 April 2008. Planning permission was granted on 10 January 2005, 19 months after submission. Operator of record: Bessy Bell Windfarm.
Planning and build timeline
| Application submitted | 3 June 2003 |
| Permission granted | 10 January 2005 19 months after submission |
| Operational | 24 April 2008 39 months after consent |
Screening a site of your own?
Derry City and Strabane approves 79% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Bessy Bell Extension’s recorded coordinate — swap in your own postcode or coordinates.
Derry City and Strabane’s record on onshore wind
Derry City and Strabane has decided 42 onshore wind schemes and approved 79%, taking a median of 29.1 months. See every onshore wind scheme decision in Derry City and Strabane →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 5 | 0.9 km |
Wind Onshore · Operational | 34.5 | 10.6 km |
Wind Onshore · Operational | 6.9 | 12 km |
Wind Onshore · Operational | 5.1 | 12.8 km |
Wind Onshore · Operational | 5 | 12.9 km |
Wind Onshore · Under Construction | 27 | 13.2 km |
Wind Onshore · Operational | 25 | 13.3 km |
Wind Onshore · Operational | 9 | 13.5 km |
How big is Bessy Bell Extension?
Bessy Bell Extension has a recorded installed capacity of 9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bessy Bell Extension?
REPD records the operator as Bessy Bell Windfarm. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bessy Bell Extension approved and built?
The application was submitted on 3 June 2003. Permission was granted on 10 January 2005, 19 months later. The site became operational on 24 April 2008, 39 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3168.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode