Renewable sites › Bessy Bell Extension
Bessy Bell Extension
Bessy Bell Extension is operational in Derry City and Strabane with a recorded capacity of 9 MW, and has been generating since 2008-04-24.
Planning and build timeline
| Application submitted | 2003-06-03 |
| Permission granted | 2005-01-10 19 months after submission |
| Operational | 2008-04-24 39 months after consent |
Derry City and Strabane’s record on onshore wind
Derry City and Strabane has decided 42 onshore wind schemes and approved 79%, taking a median of 29.1 months. See every onshore wind scheme decision in Derry City and Strabane →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Bessy Bell Wind Farm Wind Onshore · Operational | 5 | 0.9 km |
Tievenameenta Wind Onshore · Operational | 34.5 | 10.6 km |
Slieveglass Wind Onshore · Operational | 6.9 | 12 km |
Owenreagh Extension Wind Onshore · Operational | 5.1 | 12.8 km |
Owenreagh Wind Farm Wind Onshore · Operational | 5 | 12.9 km |
Pigeon Top Wind Onshore · Under Construction | 27 | 13.2 km |
Castlecraig Wind Onshore · Operational | 25 | 13.3 km |
Bin Mountain Wind Onshore · Operational | 9 | 13.5 km |
How big is Bessy Bell Extension?
Bessy Bell Extension has a recorded installed capacity of 9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bessy Bell Extension?
REPD records the operator as Bessy Bell Windfarm. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bessy Bell Extension approved and built?
The application was submitted on 2003-06-03. Permission was granted on 2005-01-10, 19 months later. The site became operational on 2008-04-24, 39 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3168.
Novarly Parcel · official public data, read properly · parcel.novarly.com