Otherton Farm

Otherton Farm is operational in Malvern Hills with a recorded capacity of 4 MW, and has been generating since 2017-03-21.

4 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-03-21
Solar Photovoltaics
Technology
Wirisol (Sun & Soil)
Malvern Hills
Authority
England

Planning and build timeline

Application submitted2015-07-29
Permission granted2015-12-18
5 months after submission
Operational2017-03-21
15 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Malvern Hills’s record on solar

Malvern Hills has decided 10 solar farms and approved 60%, taking a median of 4.7 months. See every solar farm decision in Malvern Hills

Other built sites within 15 km

SiteMWDistance
Henwick Grove - Solar Panels
Solar Photovoltaics · Operational
3.2 km
The Haven
Wind Onshore · Operational
1.26.7 km
Norton Fields Farm
Wind Onshore · Operational
1.310.1 km
Hangmans Lane
EfW Incineration · Under Construction
510.5 km
Croome Airfield Solar Farm
Solar Photovoltaics · Operational
49.914 km

How big is Otherton Farm?

Otherton Farm has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Otherton Farm?

REPD records the operator as Wirisol (Sun & Soil). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Otherton Farm approved and built?

The application was submitted on 2015-07-29. Permission was granted on 2015-12-18, 5 months later. The site became operational on 2017-03-21, 15 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5538.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council