Ormonde Offshore is an operational 150 MW offshore wind farm in DECC (S36), generating since 22 February 2012. Planning permission was granted on 4 September 2008, 38 months after submission. Operator of record: Vattenfall.

150 MW
Capacity
as recorded in REPD
Operational
Status
since 22 February 2012
Wind Offshore
Technology
Vattenfall
DECC (S36)
Authority
England

Planning and build timeline

Application submitted12 July 2005
Permission granted4 September 2008
38 months after submission
Operational22 February 2012
42 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in DECC (S36): the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Ormonde Offshore’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Wind Offshore · Operational
183.67.5 km
Wind Offshore · Operational
183.611.2 km
Wind Offshore · Operational
38911.6 km
Solar Photovoltaics · Operational
514.1 km
Wind Offshore · Operational
9014.2 km
Wind Onshore · Operational
2.414.8 km
Wind Onshore · Operational
1.214.8 km

How big is Ormonde Offshore?

Ormonde Offshore has a recorded installed capacity of 150 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Ormonde Offshore?

REPD records the operator as Vattenfall. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Ormonde Offshore approved and built?

The application was submitted on 12 July 2005. Permission was granted on 4 September 2008, 38 months later. The site became operational on 22 February 2012, 42 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2509.