Renewable sites › Barrow�
Barrow�
Barrow� is an operational 90 MW offshore wind farm in DECC (S36), generating since 1 April 2006. Planning permission was granted on 12 March 2003, 10 months after submission. Operator of record: Orsted (formerly Dong Energy).
Planning and build timeline
| Application submitted | 10 May 2002 |
| Permission granted | 12 March 2003 10 months after submission |
| Operational | 1 April 2006 37 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in DECC (S36): the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Barrow�’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
- Special Protection Area — Liverpool Bay
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Offshore · Operational | 389 | 10.8 km |
Wind Offshore · Operational | 150 | 14.2 km |
Battery · Operational | 49 | 14.5 km |
How big is Barrow�?
Barrow� has a recorded installed capacity of 90 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Barrow�?
REPD records the operator as Orsted (formerly Dong Energy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Barrow� approved and built?
The application was submitted on 10 May 2002. Permission was granted on 12 March 2003, 10 months later. The site became operational on 1 April 2006, 37 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2546.
Novarly Parcel · official public data, read properly · parcel.novarly.com