Walney�2 is an operational 183.6 MW offshore wind farm in DECC (S36), generating since 6 April 2012. Planning permission was granted on 7 November 2007, 19 months after submission. Operator of record: Orsted (formerly Dong Energy).

183.6 MW
Capacity
as recorded in REPD
Operational
Status
since 6 April 2012
Wind Offshore
Technology
Orsted (formerly Dong Energy)
DECC (S36)
Authority
England

Planning and build timeline

Application submitted31 March 2006
Permission granted7 November 2007
19 months after submission
Operational6 April 2012
53 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in DECC (S36): the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Walney�2’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Wind Offshore · Operational
183.67.6 km
Wind Offshore · Operational
6598.6 km
Wind Offshore · Operational
15011.2 km
Wind Offshore · Operational
38914.3 km

How big is Walney�2?

Walney�2 has a recorded installed capacity of 183.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Walney�2?

REPD records the operator as Orsted (formerly Dong Energy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Walney�2 approved and built?

The application was submitted on 31 March 2006. Permission was granted on 7 November 2007, 19 months later. The site became operational on 6 April 2012, 53 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2506.