Oak Grove Biomass Facility
Oak Grove Biomass Facility is operational in North Norfolk with a recorded capacity of 2 MW, and has been generating since 2014-03-01.
Planning and build timeline
| Application submitted | 2011-11-24 |
| Permission granted | 2012-09-25 10 months after submission |
| Operational | 2014-03-01 17 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
- Nutrient-neutrality catchment — Bure Broads and Marshes
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
H M Prison Bure Solar Photovoltaics · Operational | 0.2 | 1.2 km |
Scottow Moor - RAF Coltishall Solar Farm (Phase 1) Solar Photovoltaics · Operational | 32 | 1.5 km |
Scottow Moor - RAF Coltishall Solar Farm (Phase 2) Solar Photovoltaics · Operational | 17.9 | 1.5 km |
Mayton Wood Landfill Site Landfill Gas · Operational | 1.5 | 4 km |
Bunn's Hill Solar Park Solar Photovoltaics · Operational | 5 | 4.3 km |
Frog's Loke Solar Farm Solar Photovoltaics · Operational | 5 | 4.3 km |
Carlton Farm Solar farm Solar Photovoltaics · Operational | 5 | 4.9 km |
Salhouse Solar Farm Solar Photovoltaics · Operational | 5 | 9.4 km |
How big is Oak Grove Biomass Facility?
Oak Grove Biomass Facility has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Oak Grove Biomass Facility?
REPD records the operator as Oak Grove Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Oak Grove Biomass Facility approved and built?
The application was submitted on 2011-11-24. Permission was granted on 2012-09-25, 10 months later. The site became operational on 2014-03-01, 17 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 68.