Novarly ParcelRenewable sites

Renewable sitesBunn's Hill Solar Park

Bunn's Hill Solar Park

Bunn's Hill Solar Park is operational in North Norfolk with a recorded capacity of 5 MW, and has been generating since 2016-02-03.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-02-03
Solar Photovoltaics
Technology
Solar Century/ Bluefield Solar
North Norfolk
Authority
England

Planning and build timeline

Application submitted2015-06-26
Permission granted2015-10-16
4 months after submission
Operational2016-02-03
4 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Norfolk’s record on solar

North Norfolk has decided 26 solar farms and approved 100%, taking a median of 2.7 months. See every solar farm decision in North Norfolk

Other built sites within 15 km

SiteMWDistance
Frog's Loke Solar Farm
Solar Photovoltaics · Operational
50 km
Carlton Farm Solar farm
Solar Photovoltaics · Operational
50.7 km
Oak Grove Biomass Facility
Anaerobic Digestion · Operational
24.3 km
Scottow Moor - RAF Coltishall Solar Farm (Phase 2)
Solar Photovoltaics · Operational
17.95.6 km
Scottow Moor - RAF Coltishall Solar Farm (Phase 1)
Solar Photovoltaics · Operational
325.6 km
H M Prison Bure
Solar Photovoltaics · Operational
0.25.6 km
Mayton Wood Landfill Site
Landfill Gas · Operational
1.58.3 km
Salhouse Solar Farm
Solar Photovoltaics · Operational
512.2 km

How big is Bunn's Hill Solar Park?

Bunn's Hill Solar Park has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bunn's Hill Solar Park?

REPD records the operator as Solar Century/ Bluefield Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bunn's Hill Solar Park approved and built?

The application was submitted on 2015-06-26. Permission was granted on 2015-10-16, 4 months later. The site became operational on 2016-02-03, 4 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5453.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council