Renewable sites › H M Prison Bure
H M Prison Bure
H M Prison Bure is operational in North Norfolk with a recorded capacity of 0.2 MW, and has been generating since 2021-03-01.
Planning and build timeline
| Application submitted | 2020-04-30 |
| Permission granted | 2020-06-25 2 months after submission |
| Operational | 2021-03-01 8 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.
- Conservation area — RAF Coltishall (Badersfield, Scottow)
- Nutrient-neutrality catchment — Bure Broads and Marshes
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
North Norfolk’s record on solar
North Norfolk has decided 26 solar farms and approved 100%, taking a median of 2.7 months. See every solar farm decision in North Norfolk →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Scottow Moor - RAF Coltishall Solar Farm (Phase 2) Solar Photovoltaics · Operational | 17.9 | 0.8 km |
Scottow Moor - RAF Coltishall Solar Farm (Phase 1) Solar Photovoltaics · Operational | 32 | 0.8 km |
Oak Grove Biomass Facility Anaerobic Digestion · Operational | 2 | 1.2 km |
Mayton Wood Landfill Site Landfill Gas · Operational | 1.5 | 2.7 km |
Frog's Loke Solar Farm Solar Photovoltaics · Operational | 5 | 5.6 km |
Bunn's Hill Solar Park Solar Photovoltaics · Operational | 5 | 5.6 km |
Carlton Farm Solar farm Solar Photovoltaics · Operational | 5 | 6.2 km |
Salhouse Solar Farm Solar Photovoltaics · Operational | 5 | 8.6 km |
How big is H M Prison Bure?
H M Prison Bure has a recorded installed capacity of 0.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates H M Prison Bure?
REPD records the operator as Arcadis / Ministry of Justice. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was H M Prison Bure approved and built?
The application was submitted on 2020-04-30. Permission was granted on 2020-06-25, 2 months later. The site became operational on 2021-03-01, 8 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7928.