Northwick Estate (Extension) is an operational 2.2 MW solar farm in Cotswold, generating since 31 May 2013. Planning permission was granted on 5 March 2013, 4 months after submission. Operator of record: Northwick Power Ltd.

2.2 MW
Capacity
as recorded in REPD
Operational
Status
since 31 May 2013
Solar Photovoltaics
Technology
Northwick Power Ltd
Cotswold
Authority
England

Planning and build timeline

Application submitted13 November 2012
Permission granted5 March 2013
4 months after submission
Operational31 May 2013
3 months after consent

Screening a site of your own?

RedlineUK · £39

Cotswold approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Northwick Estate (Extension)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cotswold’s record on solar

Cotswold has decided 18 solar farms and approved 100%, taking a median of 3.8 months. See every solar farm decision in Cotswold

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
50.1 km
Battery · Operational
14.9 km
Solar Photovoltaics · Operational
46.9 km
Solar Photovoltaics · Operational
0.158 km
Solar Photovoltaics · Operational
2.89.1 km
Solar Photovoltaics · Operational
229.4 km
Battery · Operational
11.2 km
Solar Photovoltaics · Operational
3011.2 km

How big is Northwick Estate (Extension)?

Northwick Estate (Extension) has a recorded installed capacity of 2.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Northwick Estate (Extension)?

REPD records the operator as Northwick Power Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Northwick Estate (Extension) approved and built?

The application was submitted on 13 November 2012. Permission was granted on 5 March 2013, 4 months later. The site became operational on 31 May 2013, 3 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1731.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode