Renewable sites › North Wayton Farm
North Wayton Farm
North Wayton Farm is operational in Cornwall with a recorded capacity of 5 MW, and has been generating since 2014-03-31.
Planning and build timeline
| Application submitted | 2012-10-09 |
| Permission granted | 2013-04-09 6 months after submission |
| Operational | 2014-03-31 12 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- National Landscape (AONB) — Tamar Valley
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Cornwall’s record on solar
Cornwall has decided 146 solar farms and approved 92%, taking a median of 3.3 months. See every solar farm decision in Cornwall →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
West Kingsmill Farm Solar Park Solar Photovoltaics · Operational | 1.6 | 1.8 km |
Warleigh Barton Solar Farm Solar Photovoltaics · Operational | 5 | 4 km |
Ernesettle Solar Farm Solar Photovoltaics · Operational | 4.1 | 4.2 km |
Howton Farm Solar Photovoltaics · Operational | 4.4 | 4.6 km |
North Yard EfW EfW Incineration · Operational | 22.5 | 5.5 km |
Dartmoor Bio Power Advanced Conversion Technologies · Operational | 3.9 | 7.5 km |
Derriford Hospital Biomass (dedicated) · Operational | 1.5 | 7.9 km |
Newton Ferrers solar park Solar Photovoltaics · Operational | 19.5 | 7.9 km |
How big is North Wayton Farm?
North Wayton Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates North Wayton Farm?
REPD records the operator as KS SPV21 Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was North Wayton Farm approved and built?
The application was submitted on 2012-10-09. Permission was granted on 2013-04-09, 6 months later. The site became operational on 2014-03-31, 12 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1776.