Novarly ParcelRenewable sites

Renewable sitesDartmoor Bio Power

Dartmoor Bio Power

Dartmoor Bio Power is an operational 3.9 MW advanced conversion plant in South Hams, generating since 6 November 2013. REPD does not record the planning grant date. Operator of record: Dartmoor Bio Power 1.

3.9 MW
Capacity
as recorded in REPD
Operational
Status
since 6 November 2013
Advanced Conversion Technologies
Technology
Dartmoor Bio Power 1
South Hams
Authority
England

Planning and build timeline

Application submitted21 January 2008
Permission grantednot recorded
Operational6 November 2013

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in South Hams: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Dartmoor Bio Power’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Biomass (dedicated) · Operational
1.53.9 km
Solar Photovoltaics · Operational
54 km
Solar Photovoltaics · Operational
4.16.6 km
Solar Photovoltaics · Operational
9.57.1 km
Solar Photovoltaics · Operational
57.5 km
Solar Photovoltaics · Operational
147.6 km
EfW Incineration · Operational
22.57.9 km
Landfill Gas · Operational
1.49 km

How big is Dartmoor Bio Power?

Dartmoor Bio Power has a recorded installed capacity of 3.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Dartmoor Bio Power?

REPD records the operator as Dartmoor Bio Power 1. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Dartmoor Bio Power approved and built?

The application was submitted on 21 January 2008. REPD does not record a grant date. The site became operational on 6 November 2013.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6442.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode