Bilbo Solar Farm Energy Storage

Bilbo Solar Farm Energy Storage is a 40 MW battery storage site under construction in Aberdeenshire. Planning permission was granted on 18 October 2019, 4 months after submission. Operator of record: Green Energy International.

40 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Battery
Technology
Green Energy International
Aberdeenshire
Authority
Scotland

Planning and build timeline

Application submitted26 June 2019
Permission granted18 October 2019
4 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Aberdeenshire approves 96% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Bilbo Solar Farm Energy Storage’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Aberdeenshire’s record on battery storage

Aberdeenshire has decided 27 battery storage schemes and approved 96%, taking a median of 5.7 months. See every battery storage scheme decision in Aberdeenshire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
36.60 km
Wind Onshore · Operational
9.21.1 km
Wind Onshore · Operational
61.9 km
Wind Onshore · Under Construction
35 km
Solar Photovoltaics · Under Construction
55 km
Battery · Under Construction
5 km
Solar Photovoltaics · Under Construction
25.6 km
Wind Onshore · Operational
1.65.8 km

How big is Bilbo Solar Farm Energy Storage?

Bilbo Solar Farm Energy Storage has a recorded installed capacity of 40 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bilbo Solar Farm Energy Storage?

REPD records the operator as Green Energy International. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bilbo Solar Farm Energy Storage approved and built?

The application was submitted on 26 June 2019. Permission was granted on 18 October 2019, 4 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7020.