Mains of Hatton
Mains of Hatton is an operational 2.4 MW onshore wind farm in Aberdeenshire, generating since 20 March 2012. Planning permission was granted on 19 September 2007, 10 months after submission. Operator of record: Eco2 /GreenCAT.
Planning and build timeline
| Application submitted | 16 November 2006 |
| Permission granted | 19 September 2007 10 months after submission |
| Operational | 20 March 2012 54 months after consent |
Screening a site of your own?
Aberdeenshire approves 69% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Mains of Hatton’s recorded coordinate — swap in your own postcode or coordinates.
Aberdeenshire’s record on onshore wind
Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 1.6 | 1.6 km |
Wind Onshore · Operational | 5 | 1.6 km |
Wind Onshore · Operational | 1.6 | 4.6 km |
Wind Onshore · Operational | 4.6 | 8.4 km |
Solar Photovoltaics · Under Construction | 1.03 | 8.5 km |
Solar Photovoltaics · Under Construction | 36.6 | 9.7 km |
Battery · Under Construction | 40 | 9.7 km |
Wind Onshore · Operational | 6 | 10.5 km |
How big is Mains of Hatton?
Mains of Hatton has a recorded installed capacity of 2.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Mains of Hatton?
REPD records the operator as Eco2 /GreenCAT. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Mains of Hatton approved and built?
The application was submitted on 16 November 2006. Permission was granted on 19 September 2007, 10 months later. The site became operational on 20 March 2012, 54 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3980.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode