Land at Overside and Greenwellheads Farms
Land at Overside and Greenwellheads Farms is an operational 9.2 MW onshore wind farm in Aberdeenshire, generating since 1 November 2013. Planning permission was granted on 13 September 2011, 5 months after submission. Operator of record: Greenside Wind Energy Ltd.
Planning and build timeline
| Application submitted | 30 March 2011 |
| Permission granted | 13 September 2011 5 months after submission |
| Operational | 1 November 2013 26 months after consent |
Screening a site of your own?
Aberdeenshire approves 69% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Land at Overside and Greenwellheads Farms’s recorded coordinate — swap in your own postcode or coordinates.
Aberdeenshire’s record on onshore wind
Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Under Construction | 36.6 | 1.1 km |
Battery · Under Construction | 40 | 1.1 km |
Wind Onshore · Operational | 6 | 1.3 km |
Battery · Under Construction | — | 3.9 km |
Wind Onshore · Under Construction | 3 | 3.9 km |
Solar Photovoltaics · Under Construction | 5 | 3.9 km |
Solar Photovoltaics · Under Construction | 2 | 4.5 km |
Wind Onshore · Operational | 1.6 | 6.6 km |
How big is Land at Overside and Greenwellheads Farms?
Land at Overside and Greenwellheads Farms has a recorded installed capacity of 9.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land at Overside and Greenwellheads Farms?
REPD records the operator as Greenside Wind Energy Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land at Overside and Greenwellheads Farms approved and built?
The application was submitted on 30 March 2011. Permission was granted on 13 September 2011, 5 months later. The site became operational on 1 November 2013, 26 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3802.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode