Renewable sitesGarlenick Estate 2 - Wind Turbines

Garlenick Estate 2 - Wind Turbines

Garlenick Estate 2 - Wind Turbines is operational in Cornwall with a recorded capacity of 4 MW, and has been generating since 2015-06-18.

4 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-06-18
Wind Onshore
Technology
Airvolution Energy
Cornwall
Authority
England

Planning and build timeline

Application submitted2012-11-01
Permission granted2013-01-31
3 months after submission
Operational2015-06-18
29 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cornwall’s record on onshore wind

Cornwall has decided 35 onshore wind schemes and approved 74%, taking a median of 7.5 months. See every onshore wind scheme decision in Cornwall

Other built sites within 15 km

SiteMWDistance
Ninnis Farm Solar
Solar Photovoltaics · Operational
53.8 km
Carnemough Farm Solar Park
Solar Photovoltaics · Operational
74.2 km
Manor Farm
Solar Photovoltaics · Operational
4.74.8 km
Carloggas Farm Solar Park
Solar Photovoltaics · Operational
8.35 km
Hewas Solar Farm
Solar Photovoltaics · Operational
55 km
KERNICK MICA DAM - SOLAR FARM
Solar Photovoltaics · Operational
125.3 km
Trethosa Farm Solar Park
Solar Photovoltaics · Operational
4.85.5 km
Goonamarth Farm - Wind Turbine
Wind Onshore · Under Construction
4.36.5 km

How big is Garlenick Estate 2 - Wind Turbines?

Garlenick Estate 2 - Wind Turbines has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Garlenick Estate 2 - Wind Turbines?

REPD records the operator as Airvolution Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Garlenick Estate 2 - Wind Turbines approved and built?

The application was submitted on 2012-11-01. Permission was granted on 2013-01-31, 3 months later. The site became operational on 2015-06-18, 29 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3917.