Novarly ParcelRenewable sites

Renewable sitesNewton Downs Farm

Newton Downs Farm

Newton Downs Farm is operational in South Hams with a recorded capacity of 5 MW, and has been generating since 2017-02-15.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-02-15
Solar Photovoltaics
Technology
Core Aries (Renewable Energy)
South Hams
Authority
England

Planning and build timeline

Application submitted2015-06-26
Permission granted2016-07-15
13 months after submission
Operational2017-02-15
7 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

South Hams’s record on solar

South Hams has decided 27 solar farms and approved 93%, taking a median of 3.3 months. See every solar farm decision in South Hams

Other built sites within 15 km

SiteMWDistance
Balls Wood Solar Farm
Solar Photovoltaics · Operational
8.72.6 km
Creacombe Solar Farm
Solar Photovoltaics · Operational
7.33.9 km
Langage Solar Farm
Solar Photovoltaics · Operational
57.1 km
Luson Farm
Solar Photovoltaics · Operational
1.97.5 km
Chelson Meadow 2
Landfill Gas · Operational
1.47.9 km
Chelson Meadow Gas to Energy Scheme
Landfill Gas · Operational
1.87.9 km
Newnham Estate
Solar Photovoltaics · Operational
149.1 km
Princess Yachts Limited - Solar PV system
Solar Photovoltaics · Under Construction
0.710.6 km

How big is Newton Downs Farm?

Newton Downs Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Newton Downs Farm?

REPD records the operator as Core Aries (Renewable Energy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Newton Downs Farm approved and built?

The application was submitted on 2015-06-26. Permission was granted on 2016-07-15, 13 months later. The site became operational on 2017-02-15, 7 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5451.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council