Creacombe Solar Farm
Creacombe Solar Farm is operational in South Hams with a recorded capacity of 7.3 MW, and has been generating since 2020-01-01.
Planning and build timeline
| Application submitted | 2017-04-24 |
| Permission granted | 2018-03-14 11 months after submission |
| Operational | 2020-01-01 22 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- National Landscape (AONB) — South Devon
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
South Hams’s record on solar
South Hams has decided 27 solar farms and approved 93%, taking a median of 3.3 months. See every solar farm decision in South Hams →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Newton Downs Farm Solar Photovoltaics · Operational | 5 | 3.9 km |
Luson Farm Solar Photovoltaics · Operational | 1.9 | 4 km |
Balls Wood Solar Farm Solar Photovoltaics · Operational | 8.7 | 4.7 km |
Langage Solar Farm Solar Photovoltaics · Operational | 5 | 6.6 km |
Newnham Estate Solar Photovoltaics · Operational | 14 | 9.2 km |
Chelson Meadow 2 Landfill Gas · Operational | 1.4 | 10.8 km |
Chelson Meadow Gas to Energy Scheme Landfill Gas · Operational | 1.8 | 10.8 km |
Lee Moor China Clay Works Solar Photovoltaics · Operational | 9.5 | 12.9 km |
How big is Creacombe Solar Farm?
Creacombe Solar Farm has a recorded installed capacity of 7.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Creacombe Solar Farm?
REPD records the operator as Gnaton Farm. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Creacombe Solar Farm approved and built?
The application was submitted on 2017-04-24. Permission was granted on 2018-03-14, 11 months later. The site became operational on 2020-01-01, 22 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6591.