Novarly ParcelRenewable sites

Renewable sitesNewlands Farm (East Devon)

Newlands Farm (East Devon)

Newlands Farm (East Devon) is operational in East Devon with a recorded capacity of 5 MW, and has been generating since 2013-03-20.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-03-20
Solar Photovoltaics
Technology
TGC Renewables
East Devon
Authority
England

Planning and build timeline

Application submitted2012-07-26
Permission granted2012-11-22
4 months after submission
Operational2013-03-20
4 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Devon’s record on solar

East Devon has decided 31 solar farms and approved 87%, taking a median of 4.5 months. See every solar farm decision in East Devon

Other built sites within 15 km

SiteMWDistance
Beavor - Photovoltaic Solar Arrays
Solar Photovoltaics · Under Construction
18.90.6 km
Wyld Meadow Solar Farm
Solar Photovoltaics · Operational
4.81.3 km
Stonebarrow Farm
Solar Photovoltaics · Operational
82.3 km
Beechgrove Farm
Solar Photovoltaics · Operational
42.8 km
Axe View Solar Farm
Solar Photovoltaics · Operational
54.4 km
Marshwood Farm
Solar Photovoltaics · Operational
1.87.5 km
JB Wheaton
Battery · Operational
8.87.7 km
Wambrook Farm
Solar Photovoltaics · Operational
4.111.6 km

How big is Newlands Farm (East Devon)?

Newlands Farm (East Devon) has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Newlands Farm (East Devon)?

REPD records the operator as TGC Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Newlands Farm (East Devon) approved and built?

The application was submitted on 2012-07-26. Permission was granted on 2012-11-22, 4 months later. The site became operational on 2013-03-20, 4 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1468.