Novarly ParcelRenewable sites

Renewable sitesStonebarrow Farm

Stonebarrow Farm

Stonebarrow Farm is operational in East Devon with a recorded capacity of 8 MW, and has been generating since 2014-01-30.

8 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-01-30
Solar Photovoltaics
Technology
British Solar Renewables (formerly known as Solar Power Generation)
East Devon
Authority
England

Planning and build timeline

Application submitted2012-11-09
Permission granted2013-04-19
5 months after submission
Operational2014-01-30
9 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Devon’s record on solar

East Devon has decided 31 solar farms and approved 87%, taking a median of 4.5 months. See every solar farm decision in East Devon

Other built sites within 15 km

SiteMWDistance
Beechgrove Farm
Solar Photovoltaics · Operational
40.6 km
Wyld Meadow Solar Farm
Solar Photovoltaics · Operational
4.81 km
Beavor - Photovoltaic Solar Arrays
Solar Photovoltaics · Under Construction
18.92.2 km
Newlands Farm (East Devon)
Solar Photovoltaics · Operational
52.3 km
Axe View Solar Farm
Solar Photovoltaics · Operational
53.8 km
Marshwood Farm
Solar Photovoltaics · Operational
1.86.1 km
JB Wheaton
Battery · Operational
8.86.2 km
Goldenhaye Field Solar Farm
Solar Photovoltaics · Operational
29.9 km

How big is Stonebarrow Farm?

Stonebarrow Farm has a recorded installed capacity of 8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Stonebarrow Farm?

REPD records the operator as British Solar Renewables (formerly known as Solar Power Generation). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Stonebarrow Farm approved and built?

The application was submitted on 2012-11-09. Permission was granted on 2013-04-19, 5 months later. The site became operational on 2014-01-30, 9 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2064.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council