Renewable sites › Moy Wind Farm (2nd Application)
Moy Wind Farm (2nd Application)
Moy Wind Farm (2nd Application) is an operational 66 MW onshore wind farm in Scotland, generating since 12 May 2016. Planning permission was granted on 24 January 2014, 9 months after submission. Operator of record: Eneco.
Planning and build timeline
| Application submitted | 22 April 2013 |
| Permission granted | 24 January 2014 9 months after submission |
| Operational | 12 May 2016 28 months after consent |
Screening a site of your own?
Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Moy Wind Farm (2nd Application)’s recorded coordinate — swap in your own postcode or coordinates.
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 92 | 6.9 km |
Wind Onshore · Operational | 48.5 | 7.9 km |
Wind Onshore · Operational | 39 | 9.5 km |
Anaerobic Digestion · Operational | 2 | 14.6 km |
How big is Moy Wind Farm (2nd Application)?
Moy Wind Farm (2nd Application) has a recorded installed capacity of 66 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Moy Wind Farm (2nd Application)?
REPD records the operator as Eneco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Moy Wind Farm (2nd Application) approved and built?
The application was submitted on 22 April 2013. Permission was granted on 24 January 2014, 9 months later. The site became operational on 12 May 2016, 28 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3647.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode