Novarly ParcelRenewable sites

Renewable sitesMorayhill AD

Morayhill AD

Morayhill AD is operational in Highland with a recorded capacity of 2 MW, and has been generating since 2017-10-01.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-10-01
Anaerobic Digestion
Technology
Morayhill
Highland
Authority
Scotland

Planning and build timeline

Application submitted2015-08-26
Permission granted2015-10-27
2 months after submission
Operational2017-10-01
23 months after consent

Other built sites within 15 km

SiteMWDistance
Moy Wind Farm (2nd Application)
Wind Onshore · Operational
6614.6 km

How big is Morayhill AD?

Morayhill AD has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Morayhill AD?

REPD records the operator as Morayhill. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Morayhill AD approved and built?

The application was submitted on 2015-08-26. Permission was granted on 2015-10-27, 2 months later. The site became operational on 2017-10-01, 23 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5703.