Renewable sitesTom Nan Clach

Tom Nan Clach

Tom Nan Clach is an operational 39 MW onshore wind farm in Highland, generating since 1 March 2019. Planning permission was granted on 24 April 2018, 32 months after submission. Operator of record: Infinergy.

39 MW
Capacity
as recorded in REPD
Operational
Status
since 1 March 2019
Wind Onshore
Technology
Infinergy
Highland
Authority
Scotland

Planning and build timeline

Application submitted27 August 2015
Permission granted24 April 2018
32 months after submission
Operational1 March 2019
10 months after consent

Screening a site of your own?

RedlineUK · £39

Highland approves 63% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Tom Nan Clach’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Highland’s record on onshore wind

Highland has decided 99 onshore wind schemes and approved 63%, taking a median of 13.9 months. See every onshore wind scheme decision in Highland

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
669.5 km
Wind Onshore · Operational
48.514.2 km
Wind Onshore · Operational
9214.3 km

How big is Tom Nan Clach?

Tom Nan Clach has a recorded installed capacity of 39 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Tom Nan Clach?

REPD records the operator as Infinergy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Tom Nan Clach approved and built?

The application was submitted on 27 August 2015. Permission was granted on 24 April 2018, 32 months later. The site became operational on 1 March 2019, 10 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4420.