Renewable sites › Farr Wind Farm
Farr Wind Farm
Farr Wind Farm is an operational 92 MW onshore wind farm in Scotland, generating since 1 October 2005. Planning permission was granted on 5 October 2004, 25 months after submission. Operator of record: Innogy (formerly RWE npower).
Planning and build timeline
| Application submitted | 12 September 2002 |
| Permission granted | 5 October 2004 25 months after submission |
| Operational | 1 October 2005 12 months after consent |
Screening a site of your own?
Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Farr Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 48.5 | 1.8 km |
Wind Onshore · Operational | 66 | 6.9 km |
Wind Onshore · Under Construction | 49.9 | 12 km |
Wind Onshore · Operational | 94 | 13 km |
Wind Onshore · Operational | 39 | 14.3 km |
How big is Farr Wind Farm?
Farr Wind Farm has a recorded installed capacity of 92 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Farr Wind Farm?
REPD records the operator as Innogy (formerly RWE npower). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Farr Wind Farm approved and built?
The application was submitted on 12 September 2002. Permission was granted on 5 October 2004, 25 months later. The site became operational on 1 October 2005, 12 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4676.