Renewable planning › Solar › Hillingdon
Solar planning in Hillingdon
Hillingdon has decided 18 solar farms and approved 89% of them, taking a median of 1.8 months to decide. Consented capacity: 4 MW. 1 application still awaiting a decision.
How Hillingdon compares
Against the 298 UK authorities with 5+ solar decisions, Hillingdon sits in the 24th percentile for approval rate (4 points below the England average) and the 74th percentile for speed.
Decisions by year
Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (21)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Hillingdon Hospital, Pield Heath Road - Solar PV Panels The Hillingdon Hospitals NHS Foundation Trust · 4058/APP/2025/2070 · 1.6 mo to decide | 0.19 | Awaiting Construction | 2025-09-18 |
Airport Gate Business Centre, Harmondsworth - Solar Panels AIPUT Industrial GP Limited · 58651/APP/2025/1765 · 2.2 mo to decide | 0.15 | Awaiting Construction | 2025-09-01 |
Micro House, Bury Street - Solar Arrays Butterfly Eco Limited · 19033/APP/2025/357 · 1.8 mo to decide | — | Awaiting Construction | 2025-04-28 |
Lombardy Retail Park, J Sainsbury Plc - Solar Panels Sainsburys Supermarkets Limited · 50719/APP/2024/3136 · 1.6 mo to decide | 0.17 | Awaiting Construction | 2025-01-17 |
Hatton Cross Underground Station, Southern Perimeter Road -Solar Panels Transport For London · 49133/APP/2024/2884 · 1.4 mo to decide | 0.26 | Awaiting Construction | 2025-01-03 |
Skyline Business Park, Great South West Road - Solar Panels DSV · 74192/APP/2024/2885 · 1.3 mo to decide | 0.25 | Awaiting Construction | 2024-12-10 |
Yeading Infant School, Carlyon Road - Solar PV Systems Solar Options for Schools · 17997/APP/2024/1611 | 0.15 | Application Withdrawn | 2024-08-22 |
Hillingdon Sports & Leisure Centre - Solar Panels Ameresco Limited · 2543/APP/2023/2972 · 3.3 mo to decide | 0.22 | Awaiting Construction | 2024-01-19 |
Northwood Health And Racquet Club, Ducks Hill Road - Solar Pv Panels David Lloyd Leisure Limited · 272/APP/2023/2306 | 0.33 | Application Submitted | 2023-07-26 |
Northwood College, Maxwell Road - Solar Panels The Girls Day School Trust · 2082/APP/2023/1439 · 2.1 mo to decide | — | Awaiting Construction | 2023-07-21 |
David Lloyd Leisure, Ducks Hill Road - Solar Panels David Lloyd Leisure Limited · 272/APP/2023/1660 | 1 | Application Refused | 2023-06-09 |
Reliance Worldwide, buildings, 2A, 2B, 9 & 10 Horton Road - Solar Photovoltaic Panels Reliance Worldwide Corporation (UK) Limited · 35902/APP/2023/624 · 1.8 mo to decide | 0.64 | Awaiting Construction | 2023-04-26 |
Reliance Worldwide Corporation, buildings, 3, 4, 5, 7 & 12, Horton Road - Solar Photovoltaic Panels Reliance Worldwide Corporation (UK) Limited · 27958/APP/2023/717 · 1.8 mo to decide | 0.64 | Awaiting Construction | 2023-04-24 |
Pasadena Centre, Pasadena Close - Solar Panels Royal London UK Real Estate Fund · 65646/APP/2022/3483 · 4.4 mo to decide | 0.39 | Awaiting Construction | 2023-03-28 |
Hillingdon Hospital - Hospital Redevelopment The Hillingdon Hospitals NHS Foundation Trust · 4058/APP/2022/1788 · 7.2 mo to decide | — | Awaiting Construction | 2023-01-18 |
Skyline Business Park, Great South West Road - Solar Panels SEGRO · 74192/APP/2022/3555 · 1.7 mo to decide | 0.44 | Awaiting Construction | 2023-01-13 |
Skyline Business Park, Great South West Road - Solar Panels SEGRO · 74192/APP/2022/3541 · 1.7 mo to decide | 0.39 | Awaiting Construction | 2023-01-13 |
Swallowfield Way - Solar Panels Eurofoods Group · 74603/APP/2022/1644 · 2.6 mo to decide | 0.36 | Awaiting Construction | 2022-08-12 |
Mount Vernon Hospital - Solar Panels The Hillingdon Hospitals NHS Foundation Trust · 3807/APP/2021/2898 · 3.3 mo to decide | — | Operational | 2021-11-01 |
Land south of Holloway Lane British Solar Renewables · 1354/APP/2015/2752 | 5 | Application Withdrawn | 2015-12-17 |
Sipson Road Costain Engineering & Construction · 46223/APP/2014/1867 · 4.9 mo to decide | 6.2 | Application Refused | 2014-10-30 |
Does Hillingdon approve solar farms?
Yes — of the 18 solar farms Hillingdon has decided, 89% were approved (16 granted, 2 refused). The UK-wide rate for solar is 93%.
How long does a solar farm application take in Hillingdon?
The median time from application to decision is 1.8 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much solar capacity has Hillingdon consented?
4 MW has been consented across 16 approved schemes, with 7 MW refused. A further 1 application awaits a decision.
Other technologies in Hillingdon
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.