Renewable sites › Wastewater Treatment Works, Fraserburgh
Wastewater Treatment Works, Fraserburgh
Wastewater Treatment Works, Fraserburgh is under construction in Aberdeenshire with a recorded capacity of 1.03 MW.
Planning and build timeline
| Application submitted | 2020-09-28 |
| Permission granted | 2020-12-15 3 months after submission |
| Operational | not recorded |
Aberdeenshire’s record on solar
Aberdeenshire has decided 39 solar farms and approved 100%, taking a median of 2.1 months. See every solar farm decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
House O'Hill Wind Onshore · Operational | 5 | 7.7 km |
House O�Hill Solar Farm Solar Photovoltaics · Operational | 1.6 | 7.7 km |
Mains of Hatton Wind Onshore · Operational | 2.4 | 8.5 km |
North Red Bog Wind Onshore · Operational | 1.6 | 11.7 km |
Bilbo Solar Farm Solar Photovoltaics · Under Construction | 36.6 | 13.9 km |
Bilbo Solar Farm Energy Storage Battery · Under Construction | 40 | 13.9 km |
Greenhill Croft Wind Onshore · Operational | 4.6 | 14 km |
How big is Wastewater Treatment Works, Fraserburgh?
Wastewater Treatment Works, Fraserburgh has a recorded installed capacity of 1.03 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Wastewater Treatment Works, Fraserburgh?
REPD records the operator as Scottish Water. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Wastewater Treatment Works, Fraserburgh approved and built?
The application was submitted on 2020-09-28. Permission was granted on 2020-12-15, 3 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9523.
Novarly Parcel · official public data, read properly · parcel.novarly.com