Onshore wind planning in Harborough

Harborough has decided 5 onshore wind schemes and approved 40% of them, taking a median of 3.9 months to decide. Consented capacity: 30 MW.

40%
Approved
2 granted · 3 refused
3.9 mo
Median decision
UK 11.5 mo
30 MW
Consented
11 MW refused
1
Appeals
1 allowed on appeal

⚠️ Small caseload (5 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Harborough compares

Against the 75 UK authorities with 5+ onshore wind decisions, Harborough sits in the 12th percentile for approval rate (28 points below the England average) and the 99th percentile for speed.

Decisions by year

35Refused — 2 (2010)210Refused — 1 (2014)114
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (5)

SchemeMWStatusDecided
Redland Roof Tiles Ltd
Infinite Renewables Limited · 14/01167/FUL · 3 mo to decide
2Application Refused2014-11-20
Valley view farm
Private Developer · 10/00020/FUL · 3.3 mo to decide
1.3Application Refused2010-04-14
Airfield Farm (Leicestershire)
Gartree Wind Power Co-operative Ltd · 09/01220/FUL · 3.9 mo to decide
7.5Application Refused2010-01-27
Swinford Wind Farm
Nuon UK · 08/00506/FUL · 20.7 mo to decide
22Operational2009-12-30
Low Spinney Wind Farm
Infinis, previously Broadview Energy Developments · 09/00174/FUL · 6.7 mo to decide
8Operational2009-09-03

Does Harborough approve onshore wind schemes?

Yes — of the 5 onshore wind schemes Harborough has decided, 40% were approved (2 granted, 3 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a onshore wind scheme application take in Harborough?

The median time from application to decision is 3.9 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Harborough consented?

30 MW has been consented across 2 approved schemes, with 11 MW refused. There are no applications currently awaiting a decision.

Other technologies in Harborough

Solar in HarboroughBattery storage in Harborough

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.