Novarly ParcelRenewable planning

Renewable planning SolarHighland

Solar planning in Highland

Highland has decided 13 solar farms and approved 100% of them, taking a median of 2 months to decide. Consented capacity: 5 MW. 4 applications still awaiting a decision.

100%
Approved
13 granted · 0 refused
2 mo
Median decision
UK 2.3 mo
5 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

How Highland compares

Against the 298 UK authorities with 5+ solar decisions, Highland sits in the 77th percentile for approval rate (7 points above the England average) and the 58th percentile for speed.

Decisions by year

35Approved — 3 (2019)319Approved — 1 (2020)120Approved — 1 (2022)122Approved — 3 (2023)323Approved — 2 (2024)224Approved — 2 (2025)225Approved — 1 (2026)126
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (17)

SchemeMWStatusDecided
Longman Landfill, Stadium Road - Solar Array
The Highland Council · 26/00576/FUL
9.9Application Submitted2026-03-16
Loch Calder Water Treatment Works, Quarry Brae - Solar Panels
Scottish Water Horizons · 26/00090/FUL
0.33Application Submitted2026-01-16
Scottish Water Challenger Estate - Ground Monted Solar Panels
Scottish Water Head Office · 25/04028/CLP · 2.1 mo to decide
0.33Awaiting Construction2026-01-09
Quarry Brae - Solar PV Panels
Scottish Water National Operations Control Centre · 25/02849/FUL · 2 mo to decide
0.66Awaiting Construction2025-10-17
Loch Calder Water Treatment Work - Solar Panels
Scottish Water National Operations Control Centre · 25/02122/CLP · 1.5 mo to decide
0.66Awaiting Construction2025-09-23
Longman Pumping Station, Longman Drive - Photovoltaic Panels
Scottish Water · 24/01344/FUL · 2 mo to decide
0.65Awaiting Construction2024-06-11
Raddery Smithy - Solar PV System Installation
Raddery Sawmill Limited · 23/05176/FUL · 1.8 mo to decide
0.15Awaiting Construction2024-03-04
Raigmore Hospital, Old Perth Road - Solar Canopy
NHS Highland · 23/04285/CLP · 1.9 mo to decide
Awaiting Construction2023-11-23
Shore Road - Distillery and Visitor Centre
Dornoch Distillery · 22/06107/FUL · 9.4 mo to decide
1Awaiting Construction2023-10-31
Longman Pumping Station, Longman Drive - Photovoltaic Panels
Scottish Water · 23/01791/FUL · 3.9 mo to decide
0.65Revised2023-08-09
Feed Millakin - Solar Panels
Mowi Scotland Limited · 23/02112/FUL · 2.3 mo to decide
0.34Awaiting Construction2023-07-18
Harbro Limited, Harbour Road - Solar PV Panels
Harbro Limited · 22/05154/FUL
0.38Application Submitted2023-01-19
Wick Airport Industrial Estate - Solar Panels
Nuclear Decommissioning Authority · 22/01234/FUL · 2.8 mo to decide
0.28Awaiting Construction2022-06-22
Inverness Royal Academy
The Highland Council · 20/01072/FUL · 6.3 mo to decide
0.3Planning Permission Expired2020-09-14
Lochaber High School (Resubmission)
Highland Council · 19/02587/FUL · 2.1 mo to decide
0.3Operational2019-08-16
Alness Academy
Highland Council · 18/05963/FUL · 2 mo to decide
0.5Under Construction2019-03-29
Invergordon Academy
Highland Council · 18/05962/FUL · 1.5 mo to decide
0.2Operational2019-02-27

Does Highland approve solar farms?

Yes — of the 13 solar farms Highland has decided, 100% were approved (13 granted, 0 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Highland?

The median time from application to decision is 2 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Highland consented?

5 MW has been consented across 13 approved schemes. A further 4 applications awaits a decision.

Other technologies in Highland

Battery storage in HighlandOnshore wind in Highland

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com

Screen a specific site here · All authorities · UK property report