Renewable sitesLimebar Lane - Energy Distribution Centre

Limebar Lane - Energy Distribution Centre

Limebar Lane - Energy Distribution Centre is a solar farm under construction in North Yorkshire. Planning permission was granted on 30 August 2022, 19 months after submission. Operator of record: Northern Energy.

Capacity
as recorded in REPD
Under Construction
Status
no operational date
Solar Photovoltaics
Technology
Northern Energy
North Yorkshire
Authority
England

Planning and build timeline

Application submitted21 January 2021
Permission granted30 August 2022
19 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

North Yorkshire approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Limebar Lane - Energy Distribution Centre’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Yorkshire’s record on solar

North Yorkshire has decided 105 solar farms and approved 96%, taking a median of 2.7 months. See every solar farm decision in North Yorkshire

Other built sites within 15 km

SiteMWDistance
Anaerobic Digestion · Operational
1.13 km
EfW Incineration · Operational
273 km
Battery · Operational
339.1 km
Solar Photovoltaics · Operational
513.1 km
Solar Photovoltaics · Operational
34.714 km
Battery · Operational
2714 km
Solar Photovoltaics · Operational
514.1 km
Solar Photovoltaics · Operational
514.7 km

How big is Limebar Lane - Energy Distribution Centre?

REPD does not record an installed capacity for Limebar Lane - Energy Distribution Centre.

Who operates Limebar Lane - Energy Distribution Centre?

REPD records the operator as Northern Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Limebar Lane - Energy Distribution Centre approved and built?

The application was submitted on 21 January 2021. Permission was granted on 30 August 2022, 19 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8827.