Boscar Grange Farm is an operational 27 MW battery storage site in North Yorkshire, generating since 18 December 2019. REPD does not record the planning grant date. Operator of record: Gridserve.
Planning and build timeline
| Application submitted | 29 October 2018 |
| Permission granted | not recorded |
| Operational | 18 December 2019 |
Screening a site of your own?
North Yorkshire approves 100% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Boscar Grange Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
North Yorkshire’s record on battery storage
North Yorkshire has decided 29 battery storage schemes and approved 100%, taking a median of 10.5 months. See every battery storage scheme decision in North Yorkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 34.7 | 0 km |
Solar Photovoltaics · Operational | 5 | 0.5 km |
Solar Photovoltaics · Operational | 5 | 6.4 km |
Solar Photovoltaics · Operational | 5 | 13.9 km |
Solar Photovoltaics · Under Construction | — | 14 km |
How big is Boscar Grange Farm?
Boscar Grange Farm has a recorded installed capacity of 27 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Boscar Grange Farm?
REPD records the operator as Gridserve. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Boscar Grange Farm approved and built?
The application was submitted on 29 October 2018. REPD does not record a grant date. The site became operational on 18 December 2019.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7332.