Renewable sites › Leacann Hydro
Leacann Hydro
Leacann Hydro is an operational 1 MW hydro scheme in Argyll and Bute, generating since 15 August 2016. Planning permission was granted on 6 December 2013, 4 months after submission. Operator of record: DHG Hydro.
Planning and build timeline
| Application submitted | 29 July 2013 |
| Permission granted | 6 December 2013 4 months after submission |
| Operational | 15 August 2016 32 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Argyll and Bute: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Leacann Hydro’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Small Hydro · Operational | 3 | 5.2 km |
Wind Onshore · Operational | 19.3 | 5.5 km |
Small Hydro · Operational | 2.2 | 7.2 km |
Wind Onshore · Operational | 48.3 | 7.9 km |
Small Hydro · Operational | 1.9 | 9.5 km |
Small Hydro · Operational | 1 | 10.4 km |
Large Hydro · Operational | 6 | 14.4 km |
Wind Onshore · Operational | 33.3 | 15 km |
How big is Leacann Hydro?
Leacann Hydro has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Leacann Hydro?
REPD records the operator as DHG Hydro. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Leacann Hydro approved and built?
The application was submitted on 29 July 2013. Permission was granted on 6 December 2013, 4 months later. The site became operational on 15 August 2016, 32 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 442.