Novarly ParcelRenewable sites

Renewable sitesA'Chruach (Phase 1)

A'Chruach (Phase 1)

A'Chruach (Phase 1) is operational in Argyll and Bute with a recorded capacity of 48.3 MW, and has been generating since 2016-06-29.

48.3 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-06-29
Wind Onshore
Technology
Infinis (formerly Novera Energy)
Argyll and Bute
Authority
Scotland

Planning and build timeline

Application submitted2011-12-22
Permission granted2012-06-27
6 months after submission
Operational2016-06-29
48 months after consent

Argyll and Bute’s record on onshore wind

Argyll and Bute has decided 38 onshore wind schemes and approved 58%, taking a median of 14.7 months. See every onshore wind scheme decision in Argyll and Bute

Other built sites within 15 km

SiteMWDistance
Ederline Hydro
Small Hydro · Operational
1.93.3 km
Braevallich
Small Hydro · Operational
2.26.8 km
Leacann Hydro
Small Hydro · Operational
17.9 km
An Suidhe
Wind Onshore · Operational
19.39.3 km
Loch Gair
Large Hydro · Operational
69.3 km
Douglas Water Hydro
Small Hydro · Operational
311.9 km

How big is A'Chruach (Phase 1)?

A'Chruach (Phase 1) has a recorded installed capacity of 48.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates A'Chruach (Phase 1)?

REPD records the operator as Infinis (formerly Novera Energy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was A'Chruach (Phase 1) approved and built?

The application was submitted on 2011-12-22. Permission was granted on 2012-06-27, 6 months later. The site became operational on 2016-06-29, 48 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4331.