Renewable sites › Langley Priory, Walnut Yard (Phase 2)
Langley Priory, Walnut Yard (Phase 2)
Langley Priory, Walnut Yard (Phase 2) is an operational 6.2 MW solar farm in North West Leicestershire, generating since 1 June 2016. Planning permission was granted on 7 October 2014, 5 months after submission. Operator of record: Lark Energy.
Planning and build timeline
| Application submitted | 6 May 2014 |
| Permission granted | 7 October 2014 5 months after submission |
| Operational | 1 June 2016 20 months after consent |
Screening a site of your own?
North West Leicestershire approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Langley Priory, Walnut Yard (Phase 2)’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
North West Leicestershire’s record on solar
North West Leicestershire has decided 28 solar farms and approved 96%, taking a median of 2.7 months. See every solar farm decision in North West Leicestershire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 1.8 | 0 km |
Wind Onshore · Operational | 1 | 3.3 km |
Solar Photovoltaics · Operational | 6.1 | 5.7 km |
Solar Photovoltaics · Operational | 1.5 | 6.1 km |
Landfill Gas · Operational | 1.1 | 6.2 km |
Solar Photovoltaics · Operational | 2.8 | 7.1 km |
EfW Incineration · Operational | 42 | 7.4 km |
Anaerobic Digestion · Operational | 2 | 9.1 km |
How big is Langley Priory, Walnut Yard (Phase 2)?
Langley Priory, Walnut Yard (Phase 2) has a recorded installed capacity of 6.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Langley Priory, Walnut Yard (Phase 2)?
REPD records the operator as Lark Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Langley Priory, Walnut Yard (Phase 2) approved and built?
The application was submitted on 6 May 2014. Permission was granted on 7 October 2014, 5 months later. The site became operational on 1 June 2016, 20 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5119.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode