Renewable sites › East Midlands Airport
East Midlands Airport
East Midlands Airport is an operational 1 MW onshore wind farm in North West Leicestershire, generating since 10 May 2011. Planning permission was granted on 28 March 2008, 7 months after submission. Operator of record: Wind Direct.
Planning and build timeline
| Application submitted | 31 August 2007 |
| Permission granted | 28 March 2008 7 months after submission |
| Operational | 10 May 2011 37 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in North West Leicestershire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with East Midlands Airport’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 6.1 | 2.9 km |
Solar Photovoltaics · Operational | 6.2 | 3.3 km |
Solar Photovoltaics · Operational | 1.8 | 3.3 km |
Solar Photovoltaics · Operational | 1.5 | 3.8 km |
EfW Incineration · Operational | 42 | 8.8 km |
Landfill Gas · Operational | 1.1 | 9.3 km |
Solar Photovoltaics · Operational | 2.8 | 10.2 km |
Wind Onshore · Operational | 5 | 10.3 km |
How big is East Midlands Airport?
East Midlands Airport has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates East Midlands Airport?
REPD records the operator as Wind Direct. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was East Midlands Airport approved and built?
The application was submitted on 31 August 2007. Permission was granted on 28 March 2008, 7 months later. The site became operational on 10 May 2011, 37 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4113.