Land to the South of 15 Lough Road

Land to the South of 15 Lough Road is an operational 4.8 MW solar farm in Lisburn and Castlereagh, generating since 7 April 2016. Planning permission was granted on 18 July 2014, 8 months after submission. Operator of record: Lightsource Renewable Energy.

4.8 MW
Capacity
as recorded in REPD
Operational
Status
since 7 April 2016
Solar Photovoltaics
Technology
Lightsource Renewable Energy
Lisburn and Castlereagh
Authority
Northern Ireland

Planning and build timeline

Application submitted19 November 2013
Permission granted18 July 2014
8 months after submission
Operational7 April 2016
21 months after consent

Screening a site of your own?

RedlineUK · £39

Lisburn and Castlereagh approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Land to the South of 15 Lough Road’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Lisburn and Castlereagh’s record on solar

Lisburn and Castlereagh has decided 6 solar farms and approved 100%, taking a median of 9.3 months. See every solar farm decision in Lisburn and Castlereagh

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
25.20.7 km
Solar Photovoltaics · Operational
6.55.5 km
Solar Photovoltaics · Operational
6.55.8 km
Solar Photovoltaics · Operational
25.75.9 km
Solar Photovoltaics · Operational
13.57.4 km
Solar Photovoltaics · Operational
78.3 km
Solar Photovoltaics · Operational
109.9 km
Wind Onshore · Operational
13.810.9 km

How big is Land to the South of 15 Lough Road?

Land to the South of 15 Lough Road has a recorded installed capacity of 4.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land to the South of 15 Lough Road?

REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land to the South of 15 Lough Road approved and built?

The application was submitted on 19 November 2013. Permission was granted on 18 July 2014, 8 months later. The site became operational on 7 April 2016, 21 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1296.