Renewable sites › Land To The North Of Moor Farm
Land To The North Of Moor Farm
Land To The North Of Moor Farm is an operational 3.8 MW solar farm in Shropshire, generating since 11 March 2017. Planning permission was granted on 6 January 2016, 8 months after submission. Operator of record: Navitas Project.
Planning and build timeline
| Application submitted | 14 May 2015 |
| Permission granted | 6 January 2016 8 months after submission |
| Operational | 11 March 2017 14 months after consent |
Screening a site of your own?
Shropshire approves 94% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Land To The North Of Moor Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Shropshire’s record on solar
Shropshire has decided 68 solar farms and approved 94%, taking a median of 3.2 months. See every solar farm decision in Shropshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 14.4 | 4.4 km |
Anaerobic Digestion · Operational | 1 | 5.8 km |
Biomass (dedicated) · Operational | 1.1 | 6 km |
EfW Incineration · Operational | 8 | 11.6 km |
Solar Photovoltaics · Operational | 20 | 13.2 km |
Solar Photovoltaics · Operational | 8.9 | 13.9 km |
Solar Photovoltaics · Operational | 8.2 | 14.1 km |
Solar Photovoltaics · Operational | 5 | 14.7 km |
How big is Land To The North Of Moor Farm?
Land To The North Of Moor Farm has a recorded installed capacity of 3.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land To The North Of Moor Farm?
REPD records the operator as Navitas Project. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land To The North Of Moor Farm approved and built?
The application was submitted on 14 May 2015. Permission was granted on 6 January 2016, 8 months later. The site became operational on 11 March 2017, 14 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5340.