Land To The North Of Moor Farm
Land To The North Of Moor Farm is operational in Shropshire with a recorded capacity of 3.8 MW, and has been generating since 2017-03-11.
Planning and build timeline
| Application submitted | 2015-05-14 |
| Permission granted | 2016-01-06 8 months after submission |
| Operational | 2017-03-11 14 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Shropshire’s record on solar
Shropshire has decided 68 solar farms and approved 94%, taking a median of 3.2 months. See every solar farm decision in Shropshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Charity Farm (Burlton Solar Farm) Solar Photovoltaics · Operational | 14.4 | 4.4 km |
Abbots moor Farm Anaerobic Digester (Farm AD) Anaerobic Digestion · Operational | 1 | 5.8 km |
ABP Ellesmere Abbatoir Biomass (dedicated) · Operational | 1.1 | 6 km |
Battlefield EfW EfW Incineration · Operational | 8 | 11.6 km |
Sundorne Grove Solar Photovoltaics · Operational | 20 | 13.2 km |
Hayford Farm Solar Photovoltaics · Operational | 8.9 | 13.9 km |
Hayford Farm - extension Solar Photovoltaics · Operational | 8.2 | 14.1 km |
Ebnal Lodge Solar Photovoltaics · Operational | 5 | 14.7 km |
How big is Land To The North Of Moor Farm?
Land To The North Of Moor Farm has a recorded installed capacity of 3.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land To The North Of Moor Farm?
REPD records the operator as Navitas Project. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land To The North Of Moor Farm approved and built?
The application was submitted on 2015-05-14. Permission was granted on 2016-01-06, 8 months later. The site became operational on 2017-03-11, 14 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5340.