Solar planning in Shropshire

Shropshire has decided 68 solar farms and approved 94% of them, taking a median of 3.2 months to decide. Consented capacity: 496 MW. 14 applications still awaiting a decision.

94%
Approved
64 granted · 4 refused
3.2 mo
Median decision
UK 2.3 mo
496 MW
Consented
44 MW refused
10
Appeals
5 allowed on appeal

How Shropshire compares

Against the 298 UK authorities with 5+ solar decisions, Shropshire sits in the 38th percentile for approval rate (1 points above the England average) and the 27th percentile for speed.

Decisions by year

815Approved — 1 (2012)112Approved — 8 (2014)Refused — 1 (2014)914Approved — 7 (2015)Refused — 2 (2015)915Approved — 4 (2016)416Approved — 1 (2019)119Approved — 1 (2021)121Approved — 6 (2022)622Approved — 14 (2023)1423Approved — 7 (2024)Refused — 1 (2024)824Approved — 13 (2025)1325Approved — 1 (2026)126
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (85)

SchemeMWStatusDecided
Shrewsbury College - Solar Panels
eEnergy Group PLC · 25/04863/PSPPA · 1.4 mo to decide
0.65Awaiting Construction2026-02-18
Robert Jones & Agnes Hunt Orthopaedic Hospital, Gobowen- Solar Array
Robert Jones & Agnes Hunt Orthopaedic Hospital NHSTrust · 25/02807/FUL · 0.9 mo to decide
1.85Application Submitted2025-10-07
Merlot Chitty Farms, Betton - Solar Panels
Merlott Chitty Farms · 25/03134/PSPPA · 0.8 mo to decide
0.3Awaiting Construction2025-09-18
Royal Shrewsbury Hospital, Mytton Oak Road - Solar Canopy
Shrewsbury & Telford NHS Trust · 25/02393/PSPPA · 1.6 mo to decide
Awaiting Construction2025-08-21
Robert Jones & Agnes Hunt Orthopaedic Hospital, Gobowen - Solar Panels
The Robert Jones and Agnes Hunt Orthopaedic Hospital NHS Trust Foundation · 25/02240/PSPPA · 1.2 mo to decide
0.2Awaiting Construction2025-08-14
Robert Jones And Agnes Hunt Orthopaedic Hospital, Gobowen - Solar Panels
The Robert Jones and Agnes Hunt Orthopaedic Hospital NHS Trust Foundation · 25/02266/PSPPA · 1.2 mo to decide
0.21Awaiting Construction2025-08-14
TB Electrics, Sandford - Solar Panels
T B Electrics · 25/02408/PSPPA · 1 mo to decide
0.17Awaiting Construction2025-08-07
Robert Jones And Agnes Hunt Orthopaedic Hospital - Solar Panels
The Robert Jones and Agnes Hunt Orthopaedic Hospital NHS Trust Foundation · 25/01911/PSPPA · 1.8 mo to decide
Awaiting Construction2025-07-22
Lower Heath Farm, Lower Heath - Solar Panels
Alan Simpson Farming Limited · 25/01785/FUL · 1.1 mo to decide
0.56Awaiting Construction2025-06-25
Berllandeg Farm, Rhoswiel - Solar Panels
Igreen Energy · 25/01572/FUL · 1.2 mo to decide
1.28Awaiting Construction2025-06-18
Berrington Farm - Solar Array
Econergy International Limited · 22/04355/FUL · 31.1 mo to decide
30Awaiting Construction2025-05-02
The Beeches, Alkington - Solar Panels
Renewabuild Limited · 24/04440/FUL · 5 mo to decide
Awaiting Construction2025-04-23
Royal Shrewsbury Hospital, Mytton Oak Road - Solar Panels
Shrewsbury & Telford NHS Trust · 25/00417/PSPPA · 1.6 mo to decide
0.75Awaiting Construction2025-03-27
Swancote Farm -Solar Panels
Swancote Energy Limited · 24/04003/FUL · 3.2 mo to decide
5Awaiting Construction2025-01-21
Caterpillar Factory, Lancaster Road - Solar Panels
Caterpillar Shrewsbury Limited · 24/04178/PSPPA · 1.8 mo to decide
0.37Awaiting Construction2025-01-08
Severn Hospice - Solar Array
Severn Hospice Limited · 24/01139/FUL · 4.6 mo to decide
0.38Awaiting Construction2024-09-12
Superstore And Premises, London Road - Solar System
Sainsburys Supermarkets Limited · 24/03018/PSPPA
0.36Application Submitted2024-08-05
Berllandeg Farm, Rhoswiel - Solar Panels
Private Developer · 24/01380/FUL · 1.3 mo to decide
1.3Revised2024-07-04
Glovers Meadow - Ground Mounted Solar Array
Shropshire Council · 24/02237/FUL
2Application Submitted2024-06-17
Haughmond Quarry - Uffington Solar Farm
Opdenergy UK 10 Limited · 24/00724/FUL · 2.8 mo to decide
25Application Refused2024-06-07
Robert Jones and Agnes Hunt Orthopaedic Hospital, Gobowen - Solar Panels
Robert Jones & Agnes Hunt Orthopaedic Hospital NHSTrust · 24/01329/FUL · 1.4 mo to decide
0.26Awaiting Construction2024-06-05
Plas Yolyn - Solar Park
Curteis Limited · 23/04531/FUL · 6 mo to decide
Awaiting Construction2024-05-03
Robert Jones & Agnes Hunt Orthopaedic Hospital - Solar Panels
Robert Jones & Agnes Hunt Orthopaedic Hospital NHSTrust · 24/01055/PSPPA · 1.2 mo to decide
Awaiting Construction2024-04-25
Robert Jones and Agnes Hunt Orthopaedic Hospital, Gobowen - Solar Panels
Robert Jones & Agnes Hunt Orthopaedic Hospital NHSTrust · 24/01302/FUL
0.43Application Submitted2024-04-22
Belton Farm, Belton - Solar Pv System
Conrad Energy (Developments) Limited · 23/05100/FUL · 4.1 mo to decide
2.18Under Construction2024-04-03
Cheswardine Hall Residential Home - Solar Panels
Cheswardine Hall Residential Home · 23/04774/FUL · 3.9 mo to decide
0.24Awaiting Construction2024-03-11
Kemberton - Solar Farm
Vattenfall · 22/02441/FUL · 20.3 mo to decide
22Awaiting Construction2024-02-22
Benbow Business Park - Roof Monted Solar PV System
Furrows Group · 23/04084/PSPPA · 1.8 mo to decide
0.2Awaiting Construction2023-11-13
Manor Farm, Crickheath - Solar Array
Manor Farm · 23/03062/FUL · 3.1 mo to decide
1.8Awaiting Construction2023-10-25
Sainsburys Supermarkets, Dun Cow Road - Solar Panels
Sainsburys Supermarkets Limited · 23/02958/PSPPA · 1.1 mo to decide
0.18Awaiting Construction2023-10-04
Rock Farm - Solar Farm
Anglo Renewables · 22/05424/EIA · 9.8 mo to decide
40Awaiting Construction2023-09-25
Winston Farm, Ellesmere Road - Solar Array
S F Jones Limited · 23/01898/FUL · 2.6 mo to decide
1.1Awaiting Construction2023-08-10
Squirrel Lane - Solar Photovoltaic Farm
Locogen Limited · 22/02151/FUL · 13.2 mo to decide
12Awaiting Construction2023-07-07
Tramway Farm, Crickheath - Solar Array
R & E J Bowker · 23/02900/FUL
1.11Application Submitted2023-07-04
Cheswardine Hall Residential Home - Solar Panels
Cheswardine Hall Residential Home · 23/01569/FUL · 1.5 mo to decide
Revised2023-06-12
Pepperhill Solar Farm - Solar Farm & Battery Storage
Low Carbon · 22/03068/FUL · 10.5 mo to decide
23Operational2023-06-07
Church Farm, Withington - Solar Farm
Elgin Energy · 22/03486/FUL · 7.6 mo to decide
25Awaiting Construction2023-04-13
Cold Move, Maes-Y-Clawdd
Cold Move Limited · 23/00031/FUL · 1.6 mo to decide
0.83Awaiting Construction2023-04-05
Bridgnorth Garden Centre - Storage Warehouse
British Garden Centres · 22/03999/FUL · 6.5 mo to decide
Awaiting Construction2023-03-30
County Lane - Solar farm
Boultbee Brooks Renewable Energy Limited · 22/01816/FUL · 11.2 mo to decide
16Awaiting Construction2023-03-21
The Old Airfield - Solar Farm
Eaton-Upon-Tern Solar Limited · 22/01866/FUL · 9.7 mo to decide
49Awaiting Construction2023-03-09
Winston Farm, Ellesmere Road - Solar Array
S F Jones Limited · 23/00338/FUL · 1.1 mo to decide
1.1Revised2023-03-07
Tramway Farm, Crickheath - Solar Array
R & E J Bowker · 22/05430/FUL · 2.5 mo to decide
1.11Revised2023-02-15
Syspal, Cockshutt Lane - Solar Panels
Syspal Limited · 22/05342/PSPPA · 1.5 mo to decide
0.16Awaiting Construction2023-01-20
Highbury Poultry Produce, Manor House Lane - Solar Array
Highbury Poultry Farm Produce Limited · 22/05395/FUL · 1.4 mo to decide
0.55Awaiting Construction2023-01-13
Highbury Poultry Farm Produce, Manor House Lane - Solar Panels
Highbury Poultry Farm Produce · 22/04277/PSPPA · 1.7 mo to decide
0.3Awaiting Construction2022-11-10
Kenwick Lodge, Cockshutt - Solar Array
A & J Wrench · 22/04436/FUL · 1 mo to decide
0.3Awaiting Construction2022-10-31
Brick House Farm - Solar Farm
Bluefield Renewwable Developments Limited · 22/02565/FUL · 4.7 mo to decide
49.9Awaiting Construction2022-10-21
Cefn-Y-Maes Farm, Rhydycroesau - Solar Park
Positech Energy Limited · 22/03447/FUL · 2.6 mo to decide
1.23Awaiting Construction2022-10-14
Kenwick Lodge, Cockshutt - Solar Array
Private Developer · 22/03489/FUL · 1.3 mo to decide
0.3Revised2022-09-06
Cefn-Y-Maes Farm, Rhydycroesau - Solar Park
Positech Energy Limited · 22/00350/FUL · 4.8 mo to decide
1.29Revised2022-06-29
Sansaw Business Park, Hadnall - Solar Panels
Sansaw Properties Limited · 22/01658/PSPPA · 1.8 mo to decide
1Awaiting Construction2022-05-30
Wykey Farm, Ruyton Xi Towns - Solar Array
W H Gittins & Sons · 22/01123/FUL · 2.2 mo to decide
1Awaiting Construction2022-05-13
Bubney Farm
AlphaReal · 21/01661/FUL · 6 mo to decide
40Operational2021-10-01
Bryn-Y-Plentyn Farm
CR and GM Woollam · 18/05499/FUL · 2.8 mo to decide
0.5Planning Permission Expired2019-02-20
Country Lane Solar Development
British Solar Renewables · 15/04345/FUL
4.7Application Withdrawn2017-03-01
South of Henley Hall
NESF (formerly Kronos Solar (KS SPV39)) · 15/01472/FUL · 14.2 mo to decide
5Operational2016-06-08
Land at High Point Farm
TGC Renewables · 14/04463/FUL · 16.8 mo to decide
4.5Operational2016-03-16
Land To The North Of Moor Farm
Navitas Project · 15/01805/FUL · 7.8 mo to decide
3.8Operational2016-01-06
Henley Solar Farm
Greencoat/ Renesola · 14/04930/FUL · 14 mo to decide
6.5Operational2016-01-04
Ebnal Lodge
Greencoat Capital · 15/03975/FUL · 3 mo to decide
5Operational2015-12-23
Albrighton Solar farm
Big 60 Million · 15/02787/FUL · 4.7 mo to decide
15.8Operational2015-12-14
Upper Meadowley Farm
GDL Upper Meadowley · 14/03933/FUL · 14.5 mo to decide
10.7Operational2015-11-12
Astley Solar Farm
Rockfire Capital · 15/02095/FUL · 4.6 mo to decide
5Operational2015-09-30
Ebnal Lodge Solar Farm
Elgin Energy EsCo · 14/03946/FUL · 9.1 mo to decide
15Revised2015-07-13
Sheriffhales Solar Farm
Lightsource Renewable Energy · 15/01366/FUL · 3.2 mo to decide
8.2Operational2015-07-01
Whitton Solar Farm
EBS Energy LLP · 15/01238/FUL · 3.4 mo to decide
8.6Appeal Refused2015-07-01
Bromfield Sand and Gravel
Sovereign Partners · 15/00284/FUL · 4.5 mo to decide
0.5Operational2015-06-25
Twemlows
Sunsave 27 (Twemlows)/ Vogt solar · 14/03957/FUL · 5.4 mo to decide
10Operational2015-02-20
High Trees Farm
Green Switch Developments · 14/02386/FUL · 8 mo to decide
3.8Appeal Refused2015-01-27
Sheriffhales Solar Farm
Lightsource Renewable Energy · 14/03444/FUL · 4.3 mo to decide
30.5Revised2014-12-10
Condover Airfield
Lightsource Renewable Energy · 14/03446/FUL · 3.7 mo to decide
12.3Operational2014-11-21
Pitchford
Lightsource Renewable Energy · 14/03464/FUL · 3.7 mo to decide
10.2Operational2014-11-21
Henley Solar Farm
Henley Solar Farm · 14/02807/FUL · 3.7 mo to decide
6.5Application Refused2014-10-27
Whitton solar farm
EBS Energy LLP · 14/02873/FUL · 3.9 mo to decide
8.6Revised2014-10-27
Hadley Solar Farm
Lightsource Renewable Energy · 14/02914/FUL · 3 mo to decide
6.6Operational2014-10-06
Charity Farm (Burlton Solar Farm)
Lightsource Renewable Energy · 14/02537/FUL · 3.6 mo to decide
14.4Operational2014-09-29
Sundorne Grove
Elgin Energy EsCo · 14/00759/FUL · 5.4 mo to decide
20Operational2014-08-28
Hayford Farm - extension
Green Power · 14/01760/FUL · 3.9 mo to decide
8.2Operational2014-08-26
Priest Weston
Mellington Farm · 14/01815/FUL · 2.9 mo to decide
1Operational2014-07-18
Condover (Green Farm)
NextEnergy Solar Fund · 13/03519/FUL · 4.2 mo to decide
10.2Operational2014-01-09
Hayford Farm
WS Systems Ltd · 12/03725/FUL · 3.3 mo to decide
8.9Operational2012-12-20
Oakridge Farm
Oakridge Farm Limited · 11/01193/FUL · 2.1 mo to decide
2Abandoned2011-06-02
Kerry Ingredients & Flavours - Solar Panels
Big Solar Co-op
0.3Under Construction
Kerry Ingredients, Clee Hill Road - Food Processing Plant
Solar community energy group & Big Solar Co-op
0.3No Application Required

Does Shropshire approve solar farms?

Yes — of the 68 solar farms Shropshire has decided, 94% were approved (64 granted, 4 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Shropshire?

The median time from application to decision is 3.2 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Shropshire consented?

496 MW has been consented across 64 approved schemes, with 44 MW refused. A further 14 applications awaits a decision.

Other technologies in Shropshire

Battery storage in ShropshireOnshore wind in Shropshire

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.