Abbots moor Farm Anaerobic Digester (Farm AD)
Abbots moor Farm Anaerobic Digester (Farm AD) is an operational 1 MW anaerobic digestion plant in Shropshire, generating since 30 November 2012. Planning permission was granted on 26 September 2011, 8 months after submission. Operator of record: Private Developer.
Planning and build timeline
| Application submitted | 2 February 2011 |
| Permission granted | 26 September 2011 8 months after submission |
| Operational | 30 November 2012 14 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Shropshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Abbots moor Farm Anaerobic Digester (Farm AD)’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Biomass (dedicated) · Operational | 1.1 | 2.7 km |
Solar Photovoltaics · Operational | 3.8 | 5.8 km |
Solar Photovoltaics · Operational | 14.4 | 8.3 km |
Solar Photovoltaics · Operational | 5 | 8.9 km |
Solar Photovoltaics · Operational | 7.2 | 11.9 km |
Solar Photovoltaics · Operational | 1 | 13.4 km |
How big is Abbots moor Farm Anaerobic Digester (Farm AD)?
Abbots moor Farm Anaerobic Digester (Farm AD) has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Abbots moor Farm Anaerobic Digester (Farm AD)?
REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Abbots moor Farm Anaerobic Digester (Farm AD) approved and built?
The application was submitted on 2 February 2011. Permission was granted on 26 September 2011, 8 months later. The site became operational on 30 November 2012, 14 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 247.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode