Renewable sites › Battlefield EfW
Battlefield EfW
Battlefield EfW is an operational 8 MW energy-from-waste plant in Shropshire, generating since 1 May 2015. Planning permission was granted on 10 January 2012, 36 months after submission. Operator of record: Veolia.
Planning and build timeline
| Application submitted | 21 January 2009 |
| Permission granted | 10 January 2012 36 months after submission |
| Operational | 1 May 2015 40 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Shropshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Battlefield EfW’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 20 | 1.6 km |
Landfill Gas · Operational | 1.3 | 8.1 km |
Solar Photovoltaics · Operational | 10.2 | 9.5 km |
Solar Photovoltaics · Operational | 14.4 | 10.7 km |
Solar Photovoltaics · Operational | 10.5 | 11.2 km |
Solar Photovoltaics · Operational | 3.8 | 11.6 km |
Solar Photovoltaics · Operational | 5 | 11.9 km |
Solar Photovoltaics · Operational | 12.3 | 12.2 km |
How big is Battlefield EfW?
Battlefield EfW has a recorded installed capacity of 8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Battlefield EfW?
REPD records the operator as Veolia. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Battlefield EfW approved and built?
The application was submitted on 21 January 2009. Permission was granted on 10 January 2012, 36 months later. The site became operational on 1 May 2015, 40 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 910.