Land at Fell View Farm (Phase 1) is operational in Preston with a recorded capacity of 4.2 MW, and has been generating since 2016-03-28.

4.2 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-03-28
Solar Photovoltaics
Technology
Anesco
Preston
Authority
England

Planning and build timeline

Application submitted2015-03-16
Permission granted2015-07-16
4 months after submission
Operational2016-03-28
8 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Preston’s record on solar

Preston has decided 10 solar farms and approved 100%, taking a median of 1.8 months. See every solar farm decision in Preston

Other built sites within 15 km

SiteMWDistance
Fell View Farm (Phase 2)
Solar Photovoltaics · Operational
2.90.2 km
BAE Samlesbury Aerodrome
Solar Photovoltaics · Operational
23.6 km
Brookhouse Mill
Solar Photovoltaics · Operational
0.37.1 km
Withnell LFS
Landfill Gas · Operational
2.310.1 km
Bilsborrow Solar Farm
Solar Photovoltaics · Operational
511 km
ENWL Training Academy
Solar Photovoltaics · Operational
0.311.7 km
The Glowhouse
Battery · Under Construction
512.3 km
Oakfield Farm - extension
Solar Photovoltaics · Operational
1.712.5 km

How big is Land at Fell View Farm (Phase 1)?

Land at Fell View Farm (Phase 1) has a recorded installed capacity of 4.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land at Fell View Farm (Phase 1)?

REPD records the operator as Anesco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land at Fell View Farm (Phase 1) approved and built?

The application was submitted on 2015-03-16. Permission was granted on 2015-07-16, 4 months later. The site became operational on 2016-03-28, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5132.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council