Novarly ParcelRenewable sites

Renewable sitesLand at East Farm

Land at East Farm

Land at East Farm is operational in Wiltshire with a recorded capacity of 6.8 MW, and has been generating since 2013-11-09.

6.8 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-11-09
Solar Photovoltaics
Technology
Anesco
Wiltshire
Authority
England

Planning and build timeline

Application submitted2013-01-03
Permission granted2013-03-19
2 months after submission
Operational2013-11-09
8 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Wiltshire’s record on solar

Wiltshire has decided 103 solar farms and approved 93%, taking a median of 4 months. See every solar farm decision in Wiltshire

Other built sites within 15 km

SiteMWDistance
Land at East Farm - extension
Solar Photovoltaics · Operational
60.7 km
Codford Biogas (Waste AD)
Anaerobic Digestion · Operational
3.70.7 km
East Codford Solar Farm Extension Phase 3
Solar Photovoltaics · Operational
180.8 km
Lower End Farm
Solar Photovoltaics · Operational
4.914.3 km
Westbury (Closed) Landfill Site
Solar Photovoltaics · Operational
3.514.4 km
Westbury Landfill Scheme
Landfill Gas · Operational
1.114.9 km

How big is Land at East Farm?

Land at East Farm has a recorded installed capacity of 6.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land at East Farm?

REPD records the operator as Anesco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land at East Farm approved and built?

The application was submitted on 2013-01-03. Permission was granted on 2013-03-19, 2 months later. The site became operational on 2013-11-09, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1748.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council