East Codford Solar Farm Extension Phase 3

East Codford Solar Farm Extension Phase 3 is operational in Wiltshire with a recorded capacity of 18 MW, and has been generating since 2022-09-01.

18 MW
Capacity
as recorded in REPD
Operational
Status
since 2022-09-01
Solar Photovoltaics
Technology
Centrica Plc
Wiltshire
Authority
England

Planning and build timeline

Application submitted2019-04-08
Permission granted2020-12-18
20 months after submission
Operational2022-09-01
20 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Wiltshire’s record on solar

Wiltshire has decided 103 solar farms and approved 93%, taking a median of 4 months. See every solar farm decision in Wiltshire

Other built sites within 15 km

SiteMWDistance
Land at East Farm - extension
Solar Photovoltaics · Operational
60.5 km
Land at East Farm
Solar Photovoltaics · Operational
6.80.8 km
Codford Biogas (Waste AD)
Anaerobic Digestion · Operational
3.70.9 km
Lower End Farm
Solar Photovoltaics · Operational
4.914.4 km
Westbury (Closed) Landfill Site
Solar Photovoltaics · Operational
3.515 km

How big is East Codford Solar Farm Extension Phase 3?

East Codford Solar Farm Extension Phase 3 has a recorded installed capacity of 18 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates East Codford Solar Farm Extension Phase 3?

REPD records the operator as Centrica Plc. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was East Codford Solar Farm Extension Phase 3 approved and built?

The application was submitted on 2019-04-08. Permission was granted on 2020-12-18, 20 months later. The site became operational on 2022-09-01, 20 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7405.