Renewable sites › Land at East Farm - extension
Land at East Farm - extension
Land at East Farm - extension is an operational 6 MW solar farm in Wiltshire, generating since 1 March 2016. Planning permission was granted on 7 January 2014, 3 months after submission. Operator of record: J.M. Stratton & Co..
Planning and build timeline
| Application submitted | 9 October 2013 |
| Permission granted | 7 January 2014 3 months after submission |
| Operational | 1 March 2016 26 months after consent |
Screening a site of your own?
Wiltshire approves 93% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Land at East Farm - extension’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Nutrient-neutrality catchment — River Avon SAC
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Wiltshire’s record on solar
Wiltshire has decided 103 solar farms and approved 93%, taking a median of 4 months. See every solar farm decision in Wiltshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Anaerobic Digestion · Operational | 3.7 | 0.4 km |
Solar Photovoltaics · Operational | 18 | 0.5 km |
Solar Photovoltaics · Operational | 6.8 | 0.7 km |
Solar Photovoltaics · Operational | 4.9 | 14.8 km |
How big is Land at East Farm - extension?
Land at East Farm - extension has a recorded installed capacity of 6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land at East Farm - extension?
REPD records the operator as J.M. Stratton & Co.. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land at East Farm - extension approved and built?
The application was submitted on 9 October 2013. Permission was granted on 7 January 2014, 3 months later. The site became operational on 1 March 2016, 26 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1915.