Knoxbridge Farm is under construction in Tunbridge Wells with a recorded capacity of 2 MW.
Planning and build timeline
| Application submitted | 2015-06-04 |
| Permission granted | 2015-09-03 3 months after submission |
| Operational | not recorded |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Widehurst Farm Solar Photovoltaics · Operational | 5 | 4.3 km |
Huggin's Hall Battery · Operational | 40 | 6.6 km |
Maidstone Road, Horsmonden - Paddock Solar Farm Solar Photovoltaics · Under Construction | 49.9 | 9.1 km |
Churn Lane, Horsmonden Solar Panels Solar Photovoltaics · Operational | 0.5 | 9.4 km |
Paddock Wood Solar Photovoltaics · Operational | 9.2 | 11.2 km |
Former Pluckley Landfill Site Landfill Gas · Operational | 1 | 14 km |
East Lenham Solar Farm Solar Photovoltaics · Operational | 6.6 | 14.1 km |
Capel Grange Solar Park Solar Photovoltaics · Operational | 6.6 | 14.9 km |
How big is Knoxbridge Farm?
Knoxbridge Farm has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Knoxbridge Farm?
REPD records the operator as Fridays & Rika Biofuels. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Knoxbridge Farm approved and built?
The application was submitted on 2015-06-04. Permission was granted on 2015-09-03, 3 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5561.