Novarly ParcelRenewable sites

Renewable sitesMaidstone Road, Horsmonden - Paddock Solar Farm

Maidstone Road, Horsmonden - Paddock Solar Farm

Maidstone Road, Horsmonden - Paddock Solar Farm is a 49.9 MW solar farm under construction in Tunbridge Wells. Planning permission was granted on 5 September 2023, 11 months after submission. Operator of record: Voltalia UK.

49.9 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Solar Photovoltaics
Technology
Voltalia UK
Tunbridge Wells
Authority
England

Planning and build timeline

Application submitted20 September 2022
Permission granted5 September 2023
11 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Tunbridge Wells approves 80% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Maidstone Road, Horsmonden - Paddock Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Tunbridge Wells’s record on solar

Tunbridge Wells has decided 20 solar farms and approved 80%, taking a median of 2.6 months. See every solar farm decision in Tunbridge Wells

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
0.51.6 km
Solar Photovoltaics · Operational
9.23.1 km
Solar Photovoltaics · Operational
55.3 km
Solar Photovoltaics · Operational
6.66.2 km
Solar Photovoltaics · Operational
14.37.8 km
Battery · Operational
408 km
Anaerobic Digestion · Under Construction
29.1 km

How big is Maidstone Road, Horsmonden - Paddock Solar Farm?

Maidstone Road, Horsmonden - Paddock Solar Farm has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Maidstone Road, Horsmonden - Paddock Solar Farm?

REPD records the operator as Voltalia UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Maidstone Road, Horsmonden - Paddock Solar Farm approved and built?

The application was submitted on 20 September 2022. Permission was granted on 5 September 2023, 11 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 10577.