Capel Grange Solar Park

Capel Grange Solar Park is operational in Tunbridge Wells with a recorded capacity of 6.6 MW, and has been generating since 2016-03-31.

6.6 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-03-31
Solar Photovoltaics
Technology
West Coast Energy
Tunbridge Wells
Authority
England

Planning and build timeline

Application submitted2014-12-12
Permission granted2015-04-10
4 months after submission
Operational2016-03-31
12 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Tunbridge Wells’s record on solar

Tunbridge Wells has decided 20 solar farms and approved 80%, taking a median of 2.6 months. See every solar farm decision in Tunbridge Wells

Other built sites within 15 km

SiteMWDistance
Hadlow Place solar farm
Solar Photovoltaics · Operational
14.31.6 km
Paddock Wood
Solar Photovoltaics · Operational
9.23.7 km
Churn Lane, Horsmonden Solar Panels
Solar Photovoltaics · Operational
0.55.4 km
Maidstone Road, Horsmonden - Paddock Solar Farm
Solar Photovoltaics · Under Construction
49.96.2 km
Widehurst Farm
Solar Photovoltaics · Operational
510.6 km
Kingshill Solar Farm
Solar Photovoltaics · Operational
311.5 km
Stangate Landfill Site
Landfill Gas · Operational
4.512.5 km
Offham Landfill Site - Solar PV Array
Solar Photovoltaics · Under Construction
10.212.5 km

How big is Capel Grange Solar Park?

Capel Grange Solar Park has a recorded installed capacity of 6.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Capel Grange Solar Park?

REPD records the operator as West Coast Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Capel Grange Solar Park approved and built?

The application was submitted on 2014-12-12. Permission was granted on 2015-04-10, 4 months later. The site became operational on 2016-03-31, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4936.