Renewable sites › Former Pluckley Landfill Site
Former Pluckley Landfill Site
Former Pluckley Landfill Site is an operational 1 MW landfill gas site in Ashford, generating since 1 December 2002. Planning permission was granted on 14 February 2002, 2 months after submission. Operator of record: Farley Engineering/ Kent Weald Properties/Cleanaway.
Planning and build timeline
| Application submitted | 13 December 2001 |
| Permission granted | 14 February 2002 2 months after submission |
| Operational | 1 December 2002 10 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Ashford: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Former Pluckley Landfill Site’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 6.9 | 3.8 km |
Solar Photovoltaics · Operational | 6.6 | 6.4 km |
Solar Photovoltaics · Operational | 0.17 | 9 km |
Solar Photovoltaics · Operational | 0.4 | 11.9 km |
Solar Photovoltaics · Operational | 7 | 13.5 km |
Anaerobic Digestion · Under Construction | 2 | 14 km |
How big is Former Pluckley Landfill Site?
Former Pluckley Landfill Site has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Former Pluckley Landfill Site?
REPD records the operator as Farley Engineering/ Kent Weald Properties/Cleanaway. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Former Pluckley Landfill Site approved and built?
The application was submitted on 13 December 2001. Permission was granted on 14 February 2002, 2 months later. The site became operational on 1 December 2002, 10 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 650.
Novarly Parcel · official public data, read properly · parcel.novarly.com