Renewable sitesJameson Road

Jameson Road

Jameson Road is an operational 4.3 MW landfill gas site in Wyre, generating since 13 July 2006. Planning permission was granted on 6 August 2003, 2 months after submission. Operator of record: SITA UK.

4.3 MW
Capacity
as recorded in REPD
Operational
Status
since 13 July 2006
Landfill Gas
Technology
SITA UK
Wyre
Authority
England

Planning and build timeline

Application submitted16 June 2003
Permission granted6 August 2003
2 months after submission
Operational13 July 2006
35 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Wyre: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Jameson Road’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 5 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
1.30.7 km
Anaerobic Digestion · Operational
1.90.9 km
Biomass (dedicated) · Operational
92.7 km
Solar Photovoltaics · Operational
4.59.6 km
Wind Onshore · Operational
49.9 km
Solar Photovoltaics · Under Construction
0.710.3 km
Solar Photovoltaics · Operational
4.914.2 km

How big is Jameson Road?

Jameson Road has a recorded installed capacity of 4.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Jameson Road?

REPD records the operator as SITA UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Jameson Road approved and built?

The application was submitted on 16 June 2003. Permission was granted on 6 August 2003, 2 months later. The site became operational on 13 July 2006, 35 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 708.